Skip to main content

You are currently viewing a beta version of this site; please send improvements to contact@openomb.org.

Construction, Major Projects

Schedules

TAFS: 036-0110 2022/2026 - Construction, Major Projects

Iterations:
Adjustment authority: Yes
Reporting categories: No
Previously Approved (Iteration 1) OMB Action (Iteration 2)
Line #SplitDescriptionAmount FootnotesAmountFootnotes
1000AActual - Unob Bal: Brought forward, Oct 1Line added $718,187,949.00
1000EEstimated - Unob Bal: Brought forward, Oct 1$725,000,000.00
10611Unob Bal: Antic recov of prior year unpd$80,000,000.00 $80,000,000.00
10612Unob Bal: Antic recov of prior year pd obl$5,000,000.00 $5,000,000.00
1920Total budgetary resources avail (disc. and mand.)$810,000,000.00 $803,187,949.00 See footnotes below
Footnotes for line 1920 (Current):

B1: Pursuant to section 120.21 of OMB Circular A-11, one or more lines in the Budgetary Resources section may be rounded up. As a result, those rounded lines will not match the actuals reported on the SF 133. Agency will ensure that its funds control system will only allot actuals.

6011Total Annual Basis$810,000,000.00 $803,187,949.00
6190Total budgetary resources available$810,000,000.00 See footnotes below $803,187,949.00 See footnotes below
Footnotes for line 6190 (Previous):

A1: To extent authorized by law, the estimated amount of recoveries of prior year obligations may be increased without further action by OMB. Revised estimates will be sumitted to OMB within 10 days of publicaton of end-of-month accounting reports. [Rationale: Footnote signifies that this TAFS has received or may receive an automatic apportionment.]

Footnotes for line 6190 (Current):

A1: To extent authorized by law, the estimated amount of recoveries of prior year obligations may be increased without further action by OMB. Revised estimates will be sumitted to OMB within 10 days of publicaton of end-of-month accounting reports. [Rationale: Footnote signifies that this TAFS has received or may receive an automatic apportionment.]

Footnotes

Footnotes provide further information about, or establish further legal requirements related to the use of, the funds in a given line or set of lines in an apportionment. If footnotes appear on lines 1920 or 6190, they apply to all the lines in the 1xxx and 6xxx sections, respectively. The following are all the footnotes associated with this file.

NumberText
A1
To extent authorized by law, the estimated amount of recoveries of prior year obligations may be increased without further action by OMB. Revised estimates will be sumitted to OMB within 10 days of publicaton of end-of-month accounting reports. [Rationale: Footnote signifies that this TAFS has received or may receive an automatic apportionment.]
B1
Pursuant to section 120.21 of OMB Circular A-11, one or more lines in the Budgetary Resources section may be rounded up. As a result, those rounded lines will not match the actuals reported on the SF 133. Agency will ensure that its funds control system will only allot actuals.

The following are all of the footnotes associated with the previous iteration of this file. Note that previous iterations of accounts in this file may come from multiple previous files.

NumberText
A1
To extent authorized by law, the estimated amount of recoveries of prior year obligations may be increased without further action by OMB. Revised estimates will be sumitted to OMB within 10 days of publicaton of end-of-month accounting reports. [Rationale: Footnote signifies that this TAFS has received or may receive an automatic apportionment.]

Notes about this page

  • † Links to public laws are automatically generated and are not guaranteed to be accurate.