TAFS: 036-0110 2018/2024 - Construction, Major Projects

Iterations:
Adjustment authority: Yes
Reporting categories: No
Previously Approved (Iteration 2)Current OMB Action (Iteration 3)
Line #SplitDescriptionAmount FootnotesAmountFootnotes
1000AActual - Unob Bal: Brought forward, Oct 1$83,212,673.00 $83,212,673.00 See footnotes below
Footnotes for line 1000 (A) (Current):

B1: Pursuant to section 120.21 of OMB Circular A-11, one or more lines in the Budgetary Resources section may be rounded up. As a result, those rounded lines will not match the actuals reported on the SF 133. Agency will ensure that its funds control system will only allot actuals.

1000EEstimated - Unob Bal: Brought forward, Oct 1
10611Unob Bal: Antic recov of prior year unpaid obl$10,000,000.00 $10,000,000.00
10612Unob Bal: Antic recov of prior year paid obl$5,000,000.00 $5,000,000.00
1131BA: Disc: Unob bal of approps permanently reducedLine added -$39,163,315.00 See footnotes below
Footnotes for line 1131 (Current):

B2: P.L. 118-42 (Consolidated Appropriations Act, 2024), Division A - Title II - Administrative Provisions Sec. 260 directs that, of the unobligated balances made available to the Department of Veterans Affairs from prior appropriations acts, $80,218,560 is rescinded from the Major Construction account. $41,055,245 million is reflected on line 1131 in TAFS 36-0110 2020/2024 and the remaining $39,163,315 is reflected on line 1131 in TAFS 36-0110 2018/2024.

1920Total budgetary resources avail (disc. and mand.)$98,212,673.00 See footnotes below $59,049,358.00 See footnotes below
Footnotes for line 1920 (Previous):

B1: Pursuant to section 120.21 of OMB Circular A-11, one or more lines in the Budgetary Resources section may be rounded up. As a result, those rounded lines will not match the actuals reported on the SF 133. Agency will ensure that its funds control system will only allot actuals.

Footnotes for line 1920 (Current):

B1: Pursuant to section 120.21 of OMB Circular A-11, one or more lines in the Budgetary Resources section may be rounded up. As a result, those rounded lines will not match the actuals reported on the SF 133. Agency will ensure that its funds control system will only allot actuals.

B2: P.L. 118-42 (Consolidated Appropriations Act, 2024), Division A - Title II - Administrative Provisions Sec. 260 directs that, of the unobligated balances made available to the Department of Veterans Affairs from prior appropriations acts, $80,218,560 is rescinded from the Major Construction account. $41,055,245 million is reflected on line 1131 in TAFS 36-0110 2020/2024 and the remaining $39,163,315 is reflected on line 1131 in TAFS 36-0110 2018/2024.

6011Total Annual Basis$98,212,673.00 $59,049,358.00
6190Total budgetary resources available$98,212,673.00 See footnotes below $59,049,358.00 See footnotes below
Footnotes for line 6190 (Previous):

A1: To extent authorized by law, the estimated amount of recoveries of prior year obligations may be increased without further action by OMB. Revised estimates will be sumitted to OMB within 10 days of publicaton of end-of-month accounting reports. [Rationale: Footnote signifies that this TAFS has received or may receive an automatic apportionment.]

Footnotes for line 6190 (Current):

A1: To extent authorized by law, the estimated amount of recoveries of prior year obligations may be increased without further action by OMB. Revised estimates will be sumitted to OMB within 10 days of publicaton of end-of-month accounting reports. [Rationale: Footnote signifies that this TAFS has received or may receive an automatic apportionment.]

Footnotes

Footnotes provide further information about, or establish further legal requirements related to the use of, the funds in a given line or set of lines in an apportionment. If footnotes appear on lines 1920 or 6190, they apply to all the lines in the 1xxx and 6xxx sections, respectively. The following are all the footnotes associated with this file.

NumberText
A1
To extent authorized by law, the estimated amount of recoveries of prior year obligations may be increased without further action by OMB. Revised estimates will be sumitted to OMB within 10 days of publicaton of end-of-month accounting reports. [Rationale: Footnote signifies that this TAFS has received or may receive an automatic apportionment.]
B1
Pursuant to section 120.21 of OMB Circular A-11, one or more lines in the Budgetary Resources section may be rounded up. As a result, those rounded lines will not match the actuals reported on the SF 133. Agency will ensure that its funds control system will only allot actuals.
B2
P.L. 118-42 (Consolidated Appropriations Act, 2024), Division A - Title II - Administrative Provisions Sec. 260 directs that, of the unobligated balances made available to the Department of Veterans Affairs from prior appropriations acts, $80,218,560 is rescinded from the Major Construction account. $41,055,245 million is reflected on line 1131 in TAFS 36-0110 2020/2024 and the remaining $39,163,315 is reflected on line 1131 in TAFS 36-0110 2018/2024.

The following are all of the footnotes associated with the previous iteration of this file. Note that previous iterations of accounts in this file may come from multiple previous files.

NumberText
A1
To extent authorized by law, the estimated amount of recoveries of prior year obligations may be increased without further action by OMB. Revised estimates will be sumitted to OMB within 10 days of publicaton of end-of-month accounting reports. [Rationale: Footnote signifies that this TAFS has received or may receive an automatic apportionment.]
B1
Pursuant to section 120.21 of OMB Circular A-11, one or more lines in the Budgetary Resources section may be rounded up. As a result, those rounded lines will not match the actuals reported on the SF 133. Agency will ensure that its funds control system will only allot actuals.