Office of the Inspector General
Schedules
TAFS: 089-0236 /X - Office of the Inspector General
Previously Approved (Iteration 3) | Current OMB Action (Iteration 4) | |||||
---|---|---|---|---|---|---|
Line # | Split | Description | Amount | Footnotes | Amount | Footnotes |
1000 | DA | Discretionary Actual - Unob balance brought forward, Oct 1 - Direct | $30,575,100.00 | $30,575,100.00 | ||
1000 | DA1 | Discretionary Actual - Unob balance brought forward, Oct 1 - Reim | $87,304.00 | $87,304.00 | ||
1011 | 1 | Input Unobligated balance transferred from other accounts (+) - FECM | $3,283,450.00 | See footnotes below | $3,283,450.00 | See footnotes below |
Footnotes for line 1011 (1) (Previous): | B3: Reflects transfers of additional one-tenth of one percent to Office of the Inspector General to support work for BIL/IIJA (Public Law 117-58 Sec. 303) in accordance with P.L 118-42 Sec. 307(a): FY2022: $1,839,000.00 Fossil Energy and Carbon Management $1,660,000.00 Electricity $1,200,000.00 Nuclear Energy $8,207,200.00 Energy Efficiency & Renewable Energy (EERE) $150,000.00 Cybersecurity Energy Security and Emergency Response (CESER) $5,127,250.00 Clean Energy Demonstrations $3,000.00 for Carbon Dioxide Transportation ------------------------------------------------------------- $18,186,450.00 FY2023: $1,445,450.00 Fossil Energy and Carbon Management $1,610,000.00 Electricity $1,200,000.00 Nuclear Energy $2,221,800.00 Energy Efficiency & Renewable Energy (EERE) $100,000.00 Cybersecurity Energy Security and Emergency Response (CESER) $4,426,250.00 Clean Energy Demonstrations $2,097,000.00 for Carbon Dioxide Transportation ------------------------------------------------------------- $13,099,500.00 | |||||
Footnotes for line 1011 (1) (Current): | B3: Reflects transfers of additional one-tenth of one percent to Office of the Inspector General to support work for BIL/IIJA (Public Law 117-58 Sec. 303) in accordance with P.L 118-42 Sec. 307(a): FY2022: $1,839,000.00 Fossil Energy and Carbon Management $1,660,000.00 Electricity $1,200,000.00 Nuclear Energy $8,207,200.00 Energy Efficiency & Renewable Energy (EERE) $150,000.00 Cybersecurity Energy Security and Emergency Response (CESER) $5,127,250.00 Clean Energy Demonstrations $3,000.00 for Carbon Dioxide Transportation ------------------------------------------------------------- $18,186,450.00 FY2023: $1,445,450.00 Fossil Energy and Carbon Management $1,610,000.00 Electricity $1,200,000.00 Nuclear Energy $2,221,800.00 Energy Efficiency & Renewable Energy (EERE) $100,000.00 Cybersecurity Energy Security and Emergency Response (CESER) $4,426,250.00 Clean Energy Demonstrations $2,097,000.00 for Carbon Dioxide Transportation ------------------------------------------------------------- $13,099,500.00 | |||||
1011 | 3 | Input Unobligated balance transferred from other accounts (+) - NE | $2,400,000.00 | See footnotes below | $2,400,000.00 | See footnotes below |
Footnotes for line 1011 (3) (Previous): | B3: Reflects transfers of additional one-tenth of one percent to Office of the Inspector General to support work for BIL/IIJA (Public Law 117-58 Sec. 303) in accordance with P.L 118-42 Sec. 307(a): FY2022: $1,839,000.00 Fossil Energy and Carbon Management $1,660,000.00 Electricity $1,200,000.00 Nuclear Energy $8,207,200.00 Energy Efficiency & Renewable Energy (EERE) $150,000.00 Cybersecurity Energy Security and Emergency Response (CESER) $5,127,250.00 Clean Energy Demonstrations $3,000.00 for Carbon Dioxide Transportation ------------------------------------------------------------- $18,186,450.00 FY2023: $1,445,450.00 Fossil Energy and Carbon Management $1,610,000.00 Electricity $1,200,000.00 Nuclear Energy $2,221,800.00 Energy Efficiency & Renewable Energy (EERE) $100,000.00 Cybersecurity Energy Security and Emergency Response (CESER) $4,426,250.00 Clean Energy Demonstrations $2,097,000.00 for Carbon Dioxide Transportation ------------------------------------------------------------- $13,099,500.00 | |||||
Footnotes for line 1011 (3) (Current): | B3: Reflects transfers of additional one-tenth of one percent to Office of the Inspector General to support work for BIL/IIJA (Public Law 117-58 Sec. 303) in accordance with P.L 118-42 Sec. 307(a): FY2022: $1,839,000.00 Fossil Energy and Carbon Management $1,660,000.00 Electricity $1,200,000.00 Nuclear Energy $8,207,200.00 Energy Efficiency & Renewable Energy (EERE) $150,000.00 Cybersecurity Energy Security and Emergency Response (CESER) $5,127,250.00 Clean Energy Demonstrations $3,000.00 for Carbon Dioxide Transportation ------------------------------------------------------------- $18,186,450.00 FY2023: $1,445,450.00 Fossil Energy and Carbon Management $1,610,000.00 Electricity $1,200,000.00 Nuclear Energy $2,221,800.00 Energy Efficiency & Renewable Energy (EERE) $100,000.00 Cybersecurity Energy Security and Emergency Response (CESER) $4,426,250.00 Clean Energy Demonstrations $2,097,000.00 for Carbon Dioxide Transportation ------------------------------------------------------------- $13,099,500.00 | |||||
1011 | 4 | Input Unobligated balance transferred from other accounts (+) - EERE | $10,429,000.00 | See footnotes below | $10,429,000.00 | See footnotes below |
Footnotes for line 1011 (4) (Previous): | B3: Reflects transfers of additional one-tenth of one percent to Office of the Inspector General to support work for BIL/IIJA (Public Law 117-58 Sec. 303) in accordance with P.L 118-42 Sec. 307(a): FY2022: $1,839,000.00 Fossil Energy and Carbon Management $1,660,000.00 Electricity $1,200,000.00 Nuclear Energy $8,207,200.00 Energy Efficiency & Renewable Energy (EERE) $150,000.00 Cybersecurity Energy Security and Emergency Response (CESER) $5,127,250.00 Clean Energy Demonstrations $3,000.00 for Carbon Dioxide Transportation ------------------------------------------------------------- $18,186,450.00 FY2023: $1,445,450.00 Fossil Energy and Carbon Management $1,610,000.00 Electricity $1,200,000.00 Nuclear Energy $2,221,800.00 Energy Efficiency & Renewable Energy (EERE) $100,000.00 Cybersecurity Energy Security and Emergency Response (CESER) $4,426,250.00 Clean Energy Demonstrations $2,097,000.00 for Carbon Dioxide Transportation ------------------------------------------------------------- $13,099,500.00 | |||||
Footnotes for line 1011 (4) (Current): | B3: Reflects transfers of additional one-tenth of one percent to Office of the Inspector General to support work for BIL/IIJA (Public Law 117-58 Sec. 303) in accordance with P.L 118-42 Sec. 307(a): FY2022: $1,839,000.00 Fossil Energy and Carbon Management $1,660,000.00 Electricity $1,200,000.00 Nuclear Energy $8,207,200.00 Energy Efficiency & Renewable Energy (EERE) $150,000.00 Cybersecurity Energy Security and Emergency Response (CESER) $5,127,250.00 Clean Energy Demonstrations $3,000.00 for Carbon Dioxide Transportation ------------------------------------------------------------- $18,186,450.00 FY2023: $1,445,450.00 Fossil Energy and Carbon Management $1,610,000.00 Electricity $1,200,000.00 Nuclear Energy $2,221,800.00 Energy Efficiency & Renewable Energy (EERE) $100,000.00 Cybersecurity Energy Security and Emergency Response (CESER) $4,426,250.00 Clean Energy Demonstrations $2,097,000.00 for Carbon Dioxide Transportation ------------------------------------------------------------- $13,099,500.00 | |||||
1011 | 2 | Input Unobligated balance transferred from other accounts (+) - Electricity | $3,270,000.00 | See footnotes below | $3,270,000.00 | See footnotes below |
Footnotes for line 1011 (2) (Previous): | B3: Reflects transfers of additional one-tenth of one percent to Office of the Inspector General to support work for BIL/IIJA (Public Law 117-58 Sec. 303) in accordance with P.L 118-42 Sec. 307(a): FY2022: $1,839,000.00 Fossil Energy and Carbon Management $1,660,000.00 Electricity $1,200,000.00 Nuclear Energy $8,207,200.00 Energy Efficiency & Renewable Energy (EERE) $150,000.00 Cybersecurity Energy Security and Emergency Response (CESER) $5,127,250.00 Clean Energy Demonstrations $3,000.00 for Carbon Dioxide Transportation ------------------------------------------------------------- $18,186,450.00 FY2023: $1,445,450.00 Fossil Energy and Carbon Management $1,610,000.00 Electricity $1,200,000.00 Nuclear Energy $2,221,800.00 Energy Efficiency & Renewable Energy (EERE) $100,000.00 Cybersecurity Energy Security and Emergency Response (CESER) $4,426,250.00 Clean Energy Demonstrations $2,097,000.00 for Carbon Dioxide Transportation ------------------------------------------------------------- $13,099,500.00 | |||||
Footnotes for line 1011 (2) (Current): | B3: Reflects transfers of additional one-tenth of one percent to Office of the Inspector General to support work for BIL/IIJA (Public Law 117-58 Sec. 303) in accordance with P.L 118-42 Sec. 307(a): FY2022: $1,839,000.00 Fossil Energy and Carbon Management $1,660,000.00 Electricity $1,200,000.00 Nuclear Energy $8,207,200.00 Energy Efficiency & Renewable Energy (EERE) $150,000.00 Cybersecurity Energy Security and Emergency Response (CESER) $5,127,250.00 Clean Energy Demonstrations $3,000.00 for Carbon Dioxide Transportation ------------------------------------------------------------- $18,186,450.00 FY2023: $1,445,450.00 Fossil Energy and Carbon Management $1,610,000.00 Electricity $1,200,000.00 Nuclear Energy $2,221,800.00 Energy Efficiency & Renewable Energy (EERE) $100,000.00 Cybersecurity Energy Security and Emergency Response (CESER) $4,426,250.00 Clean Energy Demonstrations $2,097,000.00 for Carbon Dioxide Transportation ------------------------------------------------------------- $13,099,500.00 | |||||
1011 | 5 | Input Unobligated balance transferred from other accounts (+) - CESER | $250,000.00 | See footnotes below | $250,000.00 | See footnotes below |
Footnotes for line 1011 (5) (Previous): | B3: Reflects transfers of additional one-tenth of one percent to Office of the Inspector General to support work for BIL/IIJA (Public Law 117-58 Sec. 303) in accordance with P.L 118-42 Sec. 307(a): FY2022: $1,839,000.00 Fossil Energy and Carbon Management $1,660,000.00 Electricity $1,200,000.00 Nuclear Energy $8,207,200.00 Energy Efficiency & Renewable Energy (EERE) $150,000.00 Cybersecurity Energy Security and Emergency Response (CESER) $5,127,250.00 Clean Energy Demonstrations $3,000.00 for Carbon Dioxide Transportation ------------------------------------------------------------- $18,186,450.00 FY2023: $1,445,450.00 Fossil Energy and Carbon Management $1,610,000.00 Electricity $1,200,000.00 Nuclear Energy $2,221,800.00 Energy Efficiency & Renewable Energy (EERE) $100,000.00 Cybersecurity Energy Security and Emergency Response (CESER) $4,426,250.00 Clean Energy Demonstrations $2,097,000.00 for Carbon Dioxide Transportation ------------------------------------------------------------- $13,099,500.00 | |||||
Footnotes for line 1011 (5) (Current): | B3: Reflects transfers of additional one-tenth of one percent to Office of the Inspector General to support work for BIL/IIJA (Public Law 117-58 Sec. 303) in accordance with P.L 118-42 Sec. 307(a): FY2022: $1,839,000.00 Fossil Energy and Carbon Management $1,660,000.00 Electricity $1,200,000.00 Nuclear Energy $8,207,200.00 Energy Efficiency & Renewable Energy (EERE) $150,000.00 Cybersecurity Energy Security and Emergency Response (CESER) $5,127,250.00 Clean Energy Demonstrations $3,000.00 for Carbon Dioxide Transportation ------------------------------------------------------------- $18,186,450.00 FY2023: $1,445,450.00 Fossil Energy and Carbon Management $1,610,000.00 Electricity $1,200,000.00 Nuclear Energy $2,221,800.00 Energy Efficiency & Renewable Energy (EERE) $100,000.00 Cybersecurity Energy Security and Emergency Response (CESER) $4,426,250.00 Clean Energy Demonstrations $2,097,000.00 for Carbon Dioxide Transportation ------------------------------------------------------------- $13,099,500.00 | |||||
1011 | 6 | Input Unobligated balance transferred from other accounts (+) - OCED | $9,553,500.00 | See footnotes below | $9,553,500.00 | See footnotes below |
Footnotes for line 1011 (6) (Previous): | B3: Reflects transfers of additional one-tenth of one percent to Office of the Inspector General to support work for BIL/IIJA (Public Law 117-58 Sec. 303) in accordance with P.L 118-42 Sec. 307(a): FY2022: $1,839,000.00 Fossil Energy and Carbon Management $1,660,000.00 Electricity $1,200,000.00 Nuclear Energy $8,207,200.00 Energy Efficiency & Renewable Energy (EERE) $150,000.00 Cybersecurity Energy Security and Emergency Response (CESER) $5,127,250.00 Clean Energy Demonstrations $3,000.00 for Carbon Dioxide Transportation ------------------------------------------------------------- $18,186,450.00 FY2023: $1,445,450.00 Fossil Energy and Carbon Management $1,610,000.00 Electricity $1,200,000.00 Nuclear Energy $2,221,800.00 Energy Efficiency & Renewable Energy (EERE) $100,000.00 Cybersecurity Energy Security and Emergency Response (CESER) $4,426,250.00 Clean Energy Demonstrations $2,097,000.00 for Carbon Dioxide Transportation ------------------------------------------------------------- $13,099,500.00 | |||||
Footnotes for line 1011 (6) (Current): | B3: Reflects transfers of additional one-tenth of one percent to Office of the Inspector General to support work for BIL/IIJA (Public Law 117-58 Sec. 303) in accordance with P.L 118-42 Sec. 307(a): FY2022: $1,839,000.00 Fossil Energy and Carbon Management $1,660,000.00 Electricity $1,200,000.00 Nuclear Energy $8,207,200.00 Energy Efficiency & Renewable Energy (EERE) $150,000.00 Cybersecurity Energy Security and Emergency Response (CESER) $5,127,250.00 Clean Energy Demonstrations $3,000.00 for Carbon Dioxide Transportation ------------------------------------------------------------- $18,186,450.00 FY2023: $1,445,450.00 Fossil Energy and Carbon Management $1,610,000.00 Electricity $1,200,000.00 Nuclear Energy $2,221,800.00 Energy Efficiency & Renewable Energy (EERE) $100,000.00 Cybersecurity Energy Security and Emergency Response (CESER) $4,426,250.00 Clean Energy Demonstrations $2,097,000.00 for Carbon Dioxide Transportation ------------------------------------------------------------- $13,099,500.00 | |||||
1011 | 7 | Input Unobligated balance transferred from other accounts (+) - CIFIA | $2,100,000.00 | See footnotes below | $2,100,000.00 | See footnotes below |
Footnotes for line 1011 (7) (Previous): | B3: Reflects transfers of additional one-tenth of one percent to Office of the Inspector General to support work for BIL/IIJA (Public Law 117-58 Sec. 303) in accordance with P.L 118-42 Sec. 307(a): FY2022: $1,839,000.00 Fossil Energy and Carbon Management $1,660,000.00 Electricity $1,200,000.00 Nuclear Energy $8,207,200.00 Energy Efficiency & Renewable Energy (EERE) $150,000.00 Cybersecurity Energy Security and Emergency Response (CESER) $5,127,250.00 Clean Energy Demonstrations $3,000.00 for Carbon Dioxide Transportation ------------------------------------------------------------- $18,186,450.00 FY2023: $1,445,450.00 Fossil Energy and Carbon Management $1,610,000.00 Electricity $1,200,000.00 Nuclear Energy $2,221,800.00 Energy Efficiency & Renewable Energy (EERE) $100,000.00 Cybersecurity Energy Security and Emergency Response (CESER) $4,426,250.00 Clean Energy Demonstrations $2,097,000.00 for Carbon Dioxide Transportation ------------------------------------------------------------- $13,099,500.00 | |||||
Footnotes for line 1011 (7) (Current): | B3: Reflects transfers of additional one-tenth of one percent to Office of the Inspector General to support work for BIL/IIJA (Public Law 117-58 Sec. 303) in accordance with P.L 118-42 Sec. 307(a): FY2022: $1,839,000.00 Fossil Energy and Carbon Management $1,660,000.00 Electricity $1,200,000.00 Nuclear Energy $8,207,200.00 Energy Efficiency & Renewable Energy (EERE) $150,000.00 Cybersecurity Energy Security and Emergency Response (CESER) $5,127,250.00 Clean Energy Demonstrations $3,000.00 for Carbon Dioxide Transportation ------------------------------------------------------------- $18,186,450.00 FY2023: $1,445,450.00 Fossil Energy and Carbon Management $1,610,000.00 Electricity $1,200,000.00 Nuclear Energy $2,221,800.00 Energy Efficiency & Renewable Energy (EERE) $100,000.00 Cybersecurity Energy Security and Emergency Response (CESER) $4,426,250.00 Clean Energy Demonstrations $2,097,000.00 for Carbon Dioxide Transportation ------------------------------------------------------------- $13,099,500.00 | |||||
1021 | Unob Bal: Recov of prior year unpaid obligations | $593.00 | $593.00 | |||
1061 | Unob Bal: Antic recov of prior year unpd/pd obl | $1,632.00 | $1,632.00 | |||
1173 | 6 | BA: Disc: Advance appropriations transferred from other accounts (+): OCED | $4,476,250.00 | See footnotes below | $4,476,250.00 | See footnotes below |
Footnotes for line 1173 (6) (Previous): | B1: Reflects appropriation transfers to support the FY 2024 IIJA/BIL for one-tenth of one percent to Office of the Inspector General in accordance with P.L. 117-58 Sec. 303: $1,446,963.00 Fossil Energy and Carbon Management $1,610,000.00 Electricity $1,200,000.00 Nuclear Energy $1,945,000.00 Energy Efficiency & Renewable Energy (EERE) $100,000.00 Cybersecurity Energy Security and Emergency Response (CESER) $4,476,250.00 Clean Energy Demonstrations ---------------------- $10,778,213.00 | |||||
Footnotes for line 1173 (6) (Current): | B1: Reflects appropriation transfers to support the FY 2024 IIJA/BIL for one-tenth of one percent to Office of the Inspector General in accordance with P.L. 117-58 Sec. 303: $1,446,963.00 Fossil Energy and Carbon Management $1,610,000.00 Electricity $1,200,000.00 Nuclear Energy $1,945,000.00 Energy Efficiency & Renewable Energy (EERE) $100,000.00 Cybersecurity Energy Security and Emergency Response (CESER) $4,476,250.00 Clean Energy Demonstrations ---------------------- $10,778,213.00 | |||||
1173 | 1 | BA: Disc: Advance appropriations transferred from other accounts (+): FECM | $1,446,963.00 | See footnotes below | $1,446,963.00 | See footnotes below |
Footnotes for line 1173 (1) (Previous): | B1: Reflects appropriation transfers to support the FY 2024 IIJA/BIL for one-tenth of one percent to Office of the Inspector General in accordance with P.L. 117-58 Sec. 303: $1,446,963.00 Fossil Energy and Carbon Management $1,610,000.00 Electricity $1,200,000.00 Nuclear Energy $1,945,000.00 Energy Efficiency & Renewable Energy (EERE) $100,000.00 Cybersecurity Energy Security and Emergency Response (CESER) $4,476,250.00 Clean Energy Demonstrations ---------------------- $10,778,213.00 | |||||
Footnotes for line 1173 (1) (Current): | B1: Reflects appropriation transfers to support the FY 2024 IIJA/BIL for one-tenth of one percent to Office of the Inspector General in accordance with P.L. 117-58 Sec. 303: $1,446,963.00 Fossil Energy and Carbon Management $1,610,000.00 Electricity $1,200,000.00 Nuclear Energy $1,945,000.00 Energy Efficiency & Renewable Energy (EERE) $100,000.00 Cybersecurity Energy Security and Emergency Response (CESER) $4,476,250.00 Clean Energy Demonstrations ---------------------- $10,778,213.00 | |||||
1173 | 2 | BA: Disc: Advance appropriations transferred from other accounts (+): Electricity | $1,610,000.00 | See footnotes below | $1,610,000.00 | See footnotes below |
Footnotes for line 1173 (2) (Previous): | B1: Reflects appropriation transfers to support the FY 2024 IIJA/BIL for one-tenth of one percent to Office of the Inspector General in accordance with P.L. 117-58 Sec. 303: $1,446,963.00 Fossil Energy and Carbon Management $1,610,000.00 Electricity $1,200,000.00 Nuclear Energy $1,945,000.00 Energy Efficiency & Renewable Energy (EERE) $100,000.00 Cybersecurity Energy Security and Emergency Response (CESER) $4,476,250.00 Clean Energy Demonstrations ---------------------- $10,778,213.00 | |||||
Footnotes for line 1173 (2) (Current): | B1: Reflects appropriation transfers to support the FY 2024 IIJA/BIL for one-tenth of one percent to Office of the Inspector General in accordance with P.L. 117-58 Sec. 303: $1,446,963.00 Fossil Energy and Carbon Management $1,610,000.00 Electricity $1,200,000.00 Nuclear Energy $1,945,000.00 Energy Efficiency & Renewable Energy (EERE) $100,000.00 Cybersecurity Energy Security and Emergency Response (CESER) $4,476,250.00 Clean Energy Demonstrations ---------------------- $10,778,213.00 | |||||
1173 | 3 | BA: Disc: Advance appropriations transferred from other accounts (+): NE | $1,200,000.00 | See footnotes below | $1,200,000.00 | See footnotes below |
Footnotes for line 1173 (3) (Previous): | B1: Reflects appropriation transfers to support the FY 2024 IIJA/BIL for one-tenth of one percent to Office of the Inspector General in accordance with P.L. 117-58 Sec. 303: $1,446,963.00 Fossil Energy and Carbon Management $1,610,000.00 Electricity $1,200,000.00 Nuclear Energy $1,945,000.00 Energy Efficiency & Renewable Energy (EERE) $100,000.00 Cybersecurity Energy Security and Emergency Response (CESER) $4,476,250.00 Clean Energy Demonstrations ---------------------- $10,778,213.00 | |||||
Footnotes for line 1173 (3) (Current): | B1: Reflects appropriation transfers to support the FY 2024 IIJA/BIL for one-tenth of one percent to Office of the Inspector General in accordance with P.L. 117-58 Sec. 303: $1,446,963.00 Fossil Energy and Carbon Management $1,610,000.00 Electricity $1,200,000.00 Nuclear Energy $1,945,000.00 Energy Efficiency & Renewable Energy (EERE) $100,000.00 Cybersecurity Energy Security and Emergency Response (CESER) $4,476,250.00 Clean Energy Demonstrations ---------------------- $10,778,213.00 | |||||
1173 | 4 | BA: Disc: Advance appropriations transferred from other accounts (+): EERE | $1,945,000.00 | See footnotes below | $1,945,000.00 | See footnotes below |
Footnotes for line 1173 (4) (Previous): | B1: Reflects appropriation transfers to support the FY 2024 IIJA/BIL for one-tenth of one percent to Office of the Inspector General in accordance with P.L. 117-58 Sec. 303: $1,446,963.00 Fossil Energy and Carbon Management $1,610,000.00 Electricity $1,200,000.00 Nuclear Energy $1,945,000.00 Energy Efficiency & Renewable Energy (EERE) $100,000.00 Cybersecurity Energy Security and Emergency Response (CESER) $4,476,250.00 Clean Energy Demonstrations ---------------------- $10,778,213.00 | |||||
Footnotes for line 1173 (4) (Current): | B1: Reflects appropriation transfers to support the FY 2024 IIJA/BIL for one-tenth of one percent to Office of the Inspector General in accordance with P.L. 117-58 Sec. 303: $1,446,963.00 Fossil Energy and Carbon Management $1,610,000.00 Electricity $1,200,000.00 Nuclear Energy $1,945,000.00 Energy Efficiency & Renewable Energy (EERE) $100,000.00 Cybersecurity Energy Security and Emergency Response (CESER) $4,476,250.00 Clean Energy Demonstrations ---------------------- $10,778,213.00 | |||||
1173 | 5 | BA: Disc: Advance appropriations transferred from other accounts (+): CESER | $100,000.00 | See footnotes below | $100,000.00 | See footnotes below |
Footnotes for line 1173 (5) (Previous): | B1: Reflects appropriation transfers to support the FY 2024 IIJA/BIL for one-tenth of one percent to Office of the Inspector General in accordance with P.L. 117-58 Sec. 303: $1,446,963.00 Fossil Energy and Carbon Management $1,610,000.00 Electricity $1,200,000.00 Nuclear Energy $1,945,000.00 Energy Efficiency & Renewable Energy (EERE) $100,000.00 Cybersecurity Energy Security and Emergency Response (CESER) $4,476,250.00 Clean Energy Demonstrations ---------------------- $10,778,213.00 | |||||
Footnotes for line 1173 (5) (Current): | B1: Reflects appropriation transfers to support the FY 2024 IIJA/BIL for one-tenth of one percent to Office of the Inspector General in accordance with P.L. 117-58 Sec. 303: $1,446,963.00 Fossil Energy and Carbon Management $1,610,000.00 Electricity $1,200,000.00 Nuclear Energy $1,945,000.00 Energy Efficiency & Renewable Energy (EERE) $100,000.00 Cybersecurity Energy Security and Emergency Response (CESER) $4,476,250.00 Clean Energy Demonstrations ---------------------- $10,778,213.00 | |||||
1176 | 1 | BA: Disc: Anticip nonexpend transfers of adv approps (net) (+ or -): FECM | $1,446,963.00 | See footnotes below | ||
Footnotes for line 1176 (1) (Current): | B4: Reflects additional one-tenth of one percent transfer of unobligated balance from FY2024 advance appropriation to Office of the Inspector General from the Infrastructure Investment and Jobs Act (Public Law 117-58 Sec. 303) in accordance with the Consolidated Appropriations Act 2024 Division D Sec. 307(c) (Public Law 118-42) of which Public Law 117-58 Sec. 303 is amended by striking “through 2026” and inserting “and 2023 and two-tenths of such amounts made available in each of fiscal years 2024 through 2026”. $1,446,963.00 Fossil Energy and Carbon Management $1,610,000.00 Electricity $1,200,000.00 Nuclear Energy $1,945,000.00 Energy Efficiency & Renewable Energy (EERE) $100,000.00 Cybersecurity Energy Security and Emergency Response (CESER) $4,476,250.00 Clean Energy Demonstrations ---------------------- $10,778,213.00 | |||||
1176 | 3 | BA:Disc:Anticip nonexpend transfers of adv approps (net) (+ or -): NE | $1,200,000.00 | See footnotes below | ||
Footnotes for line 1176 (3) (Current): | B4: Reflects additional one-tenth of one percent transfer of unobligated balance from FY2024 advance appropriation to Office of the Inspector General from the Infrastructure Investment and Jobs Act (Public Law 117-58 Sec. 303) in accordance with the Consolidated Appropriations Act 2024 Division D Sec. 307(c) (Public Law 118-42) of which Public Law 117-58 Sec. 303 is amended by striking “through 2026” and inserting “and 2023 and two-tenths of such amounts made available in each of fiscal years 2024 through 2026”. $1,446,963.00 Fossil Energy and Carbon Management $1,610,000.00 Electricity $1,200,000.00 Nuclear Energy $1,945,000.00 Energy Efficiency & Renewable Energy (EERE) $100,000.00 Cybersecurity Energy Security and Emergency Response (CESER) $4,476,250.00 Clean Energy Demonstrations ---------------------- $10,778,213.00 | |||||
1176 | 5 | BA:Disc:Anticip nonexpend transfers of adv approps (net) (+ or -): CESER | $100,000.00 | See footnotes below | ||
Footnotes for line 1176 (5) (Current): | B4: Reflects additional one-tenth of one percent transfer of unobligated balance from FY2024 advance appropriation to Office of the Inspector General from the Infrastructure Investment and Jobs Act (Public Law 117-58 Sec. 303) in accordance with the Consolidated Appropriations Act 2024 Division D Sec. 307(c) (Public Law 118-42) of which Public Law 117-58 Sec. 303 is amended by striking “through 2026” and inserting “and 2023 and two-tenths of such amounts made available in each of fiscal years 2024 through 2026”. $1,446,963.00 Fossil Energy and Carbon Management $1,610,000.00 Electricity $1,200,000.00 Nuclear Energy $1,945,000.00 Energy Efficiency & Renewable Energy (EERE) $100,000.00 Cybersecurity Energy Security and Emergency Response (CESER) $4,476,250.00 Clean Energy Demonstrations ---------------------- $10,778,213.00 | |||||
1176 | 6 | BA:Disc:Anticip nonexpend transfers of adv approps (net) (+ or -): OCED | $4,476,250.00 | See footnotes below | ||
Footnotes for line 1176 (6) (Current): | B4: Reflects additional one-tenth of one percent transfer of unobligated balance from FY2024 advance appropriation to Office of the Inspector General from the Infrastructure Investment and Jobs Act (Public Law 117-58 Sec. 303) in accordance with the Consolidated Appropriations Act 2024 Division D Sec. 307(c) (Public Law 118-42) of which Public Law 117-58 Sec. 303 is amended by striking “through 2026” and inserting “and 2023 and two-tenths of such amounts made available in each of fiscal years 2024 through 2026”. $1,446,963.00 Fossil Energy and Carbon Management $1,610,000.00 Electricity $1,200,000.00 Nuclear Energy $1,945,000.00 Energy Efficiency & Renewable Energy (EERE) $100,000.00 Cybersecurity Energy Security and Emergency Response (CESER) $4,476,250.00 Clean Energy Demonstrations ---------------------- $10,778,213.00 | |||||
1176 | 4 | BA:Disc:Anticip nonexpend transfers of adv approps (net) (+ or -): EERE | $1,945,000.00 | See footnotes below | ||
Footnotes for line 1176 (4) (Current): | B4: Reflects additional one-tenth of one percent transfer of unobligated balance from FY2024 advance appropriation to Office of the Inspector General from the Infrastructure Investment and Jobs Act (Public Law 117-58 Sec. 303) in accordance with the Consolidated Appropriations Act 2024 Division D Sec. 307(c) (Public Law 118-42) of which Public Law 117-58 Sec. 303 is amended by striking “through 2026” and inserting “and 2023 and two-tenths of such amounts made available in each of fiscal years 2024 through 2026”. $1,446,963.00 Fossil Energy and Carbon Management $1,610,000.00 Electricity $1,200,000.00 Nuclear Energy $1,945,000.00 Energy Efficiency & Renewable Energy (EERE) $100,000.00 Cybersecurity Energy Security and Emergency Response (CESER) $4,476,250.00 Clean Energy Demonstrations ---------------------- $10,778,213.00 | |||||
1176 | 2 | BA:Disc:Anticip nonexpend transfers of adv approps (net) (+ or -): Electricity | $1,610,000.00 | See footnotes below | ||
Footnotes for line 1176 (2) (Current): | B4: Reflects additional one-tenth of one percent transfer of unobligated balance from FY2024 advance appropriation to Office of the Inspector General from the Infrastructure Investment and Jobs Act (Public Law 117-58 Sec. 303) in accordance with the Consolidated Appropriations Act 2024 Division D Sec. 307(c) (Public Law 118-42) of which Public Law 117-58 Sec. 303 is amended by striking “through 2026” and inserting “and 2023 and two-tenths of such amounts made available in each of fiscal years 2024 through 2026”. $1,446,963.00 Fossil Energy and Carbon Management $1,610,000.00 Electricity $1,200,000.00 Nuclear Energy $1,945,000.00 Energy Efficiency & Renewable Energy (EERE) $100,000.00 Cybersecurity Energy Security and Emergency Response (CESER) $4,476,250.00 Clean Energy Demonstrations ---------------------- $10,778,213.00 | |||||
1700 | BA: Disc: Spending auth: Collected | $1,351,610.00 | $1,637,708.00 | |||
1701 | BA: Disc: Spending auth: Chng uncoll pymts Fed src | -$825,592.00 | -$56,638.00 | |||
1740 | BA: Disc: Spending auth:Antic colls, reimbs, other | $4,073,982.00 | $3,118,930.00 | |||
1920 | Total budgetary resources avail (disc. and mand.) | $77,328,792.00 | See footnotes below | $88,207,005.00 | See footnotes below | |
Footnotes for line 1920 (Previous): | B2: Pursuant to the authority in OMB Circular A-11 section 120.21, one or more lines on the apportionment (including lines above line 1920) may have been rounded up and as such those rounded lines will not match the actuals reported on the SF-133. DOE will ensure that its funds control system will only allot actuals. | |||||
Footnotes for line 1920 (Current): | B2: Pursuant to the authority in OMB Circular A-11 section 120.21, one or more lines on the apportionment (including lines above line 1920) may have been rounded up and as such those rounded lines will not match the actuals reported on the SF-133. DOE will ensure that its funds control system will only allot actuals. | |||||
6001 | Category A -- 1st quarter | $9,888.00 | $9,888.00 | |||
6011 | Reimbursable Work | $4,687,304.00 | $4,787,304.00 | |||
6012 | IIJA/BIL Appropriation Transfers | $72,631,600.00 | $83,409,813.00 | |||
6190 | Total budgetary resources available | $77,328,792.00 | $88,207,005.00 | |||
Footnotes
Footnotes provide further information about, or establish further legal requirements related to the use of, the funds in a given line or set of lines in an apportionment. If footnotes appear on lines 1920 or 6190, they apply to all the lines in the 1xxx and 6xxx sections, respectively. The following are all the footnotes associated with this file.
Number | Text |
---|---|
B1 | Reflects appropriation transfers to support the FY 2024 IIJA/BIL for one-tenth of one percent to Office of the Inspector
General in accordance with P.L. 117-58 Sec. 303:
$1,446,963.00 Fossil Energy and Carbon Management
$1,610,000.00 Electricity
$1,200,000.00 Nuclear Energy
$1,945,000.00 Energy Efficiency & Renewable Energy (EERE)
$100,000.00 Cybersecurity Energy Security and Emergency Response (CESER)
$4,476,250.00 Clean Energy Demonstrations
----------------------
$10,778,213.00 |
B2 | Pursuant to the authority in OMB Circular A-11 section 120.21, one or more lines on the apportionment (including lines above line 1920) may have been rounded up and as such those rounded lines will not match the actuals reported on the SF-133. DOE will ensure that its funds control system will only allot actuals. |
B3 | Reflects transfers of additional one-tenth of one percent to Office of the Inspector General to support work for BIL/IIJA (Public Law 117-58 Sec. 303) in accordance with P.L 118-42 Sec. 307(a):
FY2022:
$1,839,000.00 Fossil Energy and Carbon Management
$1,660,000.00 Electricity
$1,200,000.00 Nuclear Energy
$8,207,200.00 Energy Efficiency & Renewable Energy (EERE)
$150,000.00 Cybersecurity Energy Security and Emergency Response (CESER)
$5,127,250.00 Clean Energy Demonstrations
$3,000.00 for Carbon Dioxide Transportation
-------------------------------------------------------------
$18,186,450.00
FY2023:
$1,445,450.00 Fossil Energy and Carbon Management
$1,610,000.00 Electricity
$1,200,000.00 Nuclear Energy
$2,221,800.00 Energy Efficiency & Renewable Energy (EERE)
$100,000.00 Cybersecurity Energy Security and Emergency Response (CESER)
$4,426,250.00 Clean Energy Demonstrations
$2,097,000.00 for Carbon Dioxide Transportation
-------------------------------------------------------------
$13,099,500.00 |
B4 | Reflects additional one-tenth of one percent transfer of unobligated balance from FY2024 advance appropriation to Office of the Inspector General from the Infrastructure Investment and Jobs Act (Public Law 117-58 Sec. 303) in accordance with the Consolidated Appropriations Act 2024 Division D Sec. 307(c) (Public Law 118-42) of which Public Law 117-58 Sec. 303 is amended by striking “through 2026” and inserting “and 2023 and two-tenths of such amounts made available in each of fiscal years 2024 through 2026”.
$1,446,963.00 Fossil Energy and Carbon Management
$1,610,000.00 Electricity
$1,200,000.00 Nuclear Energy
$1,945,000.00 Energy Efficiency & Renewable Energy (EERE)
$100,000.00 Cybersecurity Energy Security and Emergency Response (CESER)
$4,476,250.00 Clean Energy Demonstrations
----------------------
$10,778,213.00 |
The following are all of the footnotes associated with the previous iteration of this file. Note that previous iterations of accounts in this file may come from multiple previous files.
Number | Text |
---|---|
B1 | Reflects appropriation transfers to support the FY 2024 IIJA/BIL for one-tenth of one percent to Office of the Inspector
General in accordance with P.L. 117-58 Sec. 303:
$1,446,963.00 Fossil Energy and Carbon Management
$1,610,000.00 Electricity
$1,200,000.00 Nuclear Energy
$1,945,000.00 Energy Efficiency & Renewable Energy (EERE)
$100,000.00 Cybersecurity Energy Security and Emergency Response (CESER)
$4,476,250.00 Clean Energy Demonstrations
----------------------
$10,778,213.00 |
B2 | Pursuant to the authority in OMB Circular A-11 section 120.21, one or more lines on the apportionment (including lines above line 1920) may have been rounded up and as such those rounded lines will not match the actuals reported on the SF-133. DOE will ensure that its funds control system will only allot actuals. |
B3 | Reflects transfers of additional one-tenth of one percent to Office of the Inspector General to support work for BIL/IIJA (Public Law 117-58 Sec. 303) in accordance with P.L 118-42 Sec. 307(a):
FY2022:
$1,839,000.00 Fossil Energy and Carbon Management
$1,660,000.00 Electricity
$1,200,000.00 Nuclear Energy
$8,207,200.00 Energy Efficiency & Renewable Energy (EERE)
$150,000.00 Cybersecurity Energy Security and Emergency Response (CESER)
$5,127,250.00 Clean Energy Demonstrations
$3,000.00 for Carbon Dioxide Transportation
-------------------------------------------------------------
$18,186,450.00
FY2023:
$1,445,450.00 Fossil Energy and Carbon Management
$1,610,000.00 Electricity
$1,200,000.00 Nuclear Energy
$2,221,800.00 Energy Efficiency & Renewable Energy (EERE)
$100,000.00 Cybersecurity Energy Security and Emergency Response (CESER)
$4,426,250.00 Clean Energy Demonstrations
$2,097,000.00 for Carbon Dioxide Transportation
-------------------------------------------------------------
$13,099,500.00 |