Railroad Rehabilitation and Improvement Direct Loan Financing Ac

Schedules

TAFS: 069-4420 /X - Railroad Rehabilitation and Improvement Direct Loan Financing Ac

Iterations:
Adjustment authority: No
Reporting categories: No
Previously Approved (Iteration 1)Current OMB Action (Iteration 2)
Line #SplitDescriptionAmount FootnotesAmountFootnotes
1000AActual - Unob Bal: Brought forward, Oct 1$25,998,414.00 $25,998,414.00
1400BA: Mand: Borrowing authority$65,884,973.00 $4,196,491,467.00
1800BA: Mand: Spending auth: Collected$1,032,454.00 $60,724,004.00
1801BA: Mand: Spending auth: Chng uncoll pymts Fed srcLine added $7,672,102.00
1840BA: Mand: Spending auth:Antic colls, reimbs, other$143,015,491.00 $149,347,740.00
1842BA: Mand: Spending auth: Antic cap tran, red debt-$80,831,875.00 -$152,077,957.00
1920Total budgetary resources avail (disc. and mand.)$155,099,457.00 See footnotes below $4,288,155,770.00 See footnotes below
Footnotes for line 1920 (Previous):

B2: Pursuant to the authority in OMB Circular A-11 section 120.21, one or more lines on the apportionment (including lines above line 1920) may have been rounded up and as such, those rounded lines will not match the actuals reported on the SF-133. Agency will ensure that its funds control system will only allot actuals.

Footnotes for line 1920 (Current):

B1: Pursuant to the authority in OMB Circular A-11 section 120.21, one or more lines on the apportionment (including lines above line 1920) may have been rounded up and as such, those rounded lines will not match the actuals reported on the SF-133. Agency will ensure that its funds control system will only allot actuals.

6011Interest to Treasury$120,887,165.00 $123,336,984.00
6012Project: Sierra Railways$31,379,805.00 $31,379,805.00
6013Project: Hudson Tunnel ProjectLine added $4,060,070,946.00
6015Negative SubsidyLine added $55,680,763.00
6016Credit Risk Premium Repayment$2,832,487.00 $2,832,487.00
6017Downward ReestimateLine added $11,719,187.00
6018Interest on Downward ReestimatesLine added $3,135,598.00
6190Total budgetary resources available$155,099,457.00 $4,288,155,770.00

Footnotes

Footnotes provide further information about, or establish further legal requirements related to the use of, the funds in a given line or set of lines in an apportionment. If footnotes appear on lines 1920 or 6190, they apply to all the lines in the 1xxx and 6xxx sections, respectively. The following are all the footnotes associated with this file.

NumberText
B1
Pursuant to the authority in OMB Circular A-11 section 120.21, one or more lines on the apportionment (including lines above line 1920) may have been rounded up and as such, those rounded lines will not match the actuals reported on the SF-133. Agency will ensure that its funds control system will only allot actuals.

The following are all of the footnotes associated with the previous iteration of this file. Note that previous iterations of accounts in this file may come from multiple previous files.

NumberText
B2
Pursuant to the authority in OMB Circular A-11 section 120.21, one or more lines on the apportionment (including lines above line 1920) may have been rounded up and as such, those rounded lines will not match the actuals reported on the SF-133. Agency will ensure that its funds control system will only allot actuals.

Notes about this page