Line #SplitDescriptionAmountFootnotes
1000DEDiscretionary - Estimated Unob Bal: Brought forward, October 1 $140,971,256
1061Unob Bal: Antic recov of prior year unpd/pd obl $1,400,000
1920Total budgetary resources avail (disc. and mand.) $142,371,256See footnotes below
Footnotes for line 1920:

B1: The majority of the funds will be used for the following projects: 1) Replace 4” galvanized dry system fire suppression piping in parking garage at Gulfport campus. 2) Replace air handling units at Gulfport campus. 3) Drainage canal repairs (phase 1) at Gulfport campus. 4) Historic buildings envelope waterproofing, masonry repointing, plaster, replace deteriorated components (phase 2) at Washington campus.

B2: Pursuant to section 120.21 of OMB Circular A-11, one or more lines in the Budgetary Resources section may be rounded up. As a result, those rounded lines will not match the actuals reported on the SF 133. Agency will ensure that its funds control system will only allot actuals.

B3: Amount transferred from 47-0616/2021-2025 pursuant section 4011 of Public Law 117-2, for the AFRH Transforming Resident-Centered Healthcare Through Modernized Electronic Health Record Systems as recommended by the Technology Modernization Board pursuant to a written agreement between GSA and the Armed Forces Retirement Home.

6011Capital $32,370,304
6012Sheridan Building Renovation $105,674,973
6013Technology Modernization Fund $4,325,979
6190Total budgetary resources available $142,371,256

Footnotes

Footnotes provide further information about, or establish further legal requirements related to the use of, the funds in a given line or set of lines in an apportionment. If footnotes appear on lines 1920 or 6190, they apply to all the lines in the 1xxx and 6xxx sections, respectively. The following are all the footnotes associated with this file.

NumberText
B1
The majority of the funds will be used for the following projects: 1) Replace 4” galvanized dry system fire suppression piping in parking garage at Gulfport campus. 2) Replace air handling units at Gulfport campus. 3) Drainage canal repairs (phase 1) at Gulfport campus. 4) Historic buildings envelope waterproofing, masonry repointing, plaster, replace deteriorated components (phase 2) at Washington campus.
B2
Pursuant to section 120.21 of OMB Circular A-11, one or more lines in the Budgetary Resources section may be rounded up. As a result, those rounded lines will not match the actuals reported on the SF 133. Agency will ensure that its funds control system will only allot actuals.
B3
Amount transferred from 47-0616/2021-2025 pursuant section 4011 of Public Law 117-2, for the AFRH Transforming Resident-Centered Healthcare Through Modernized Electronic Health Record Systems as recommended by the Technology Modernization Board pursuant to a written agreement between GSA and the Armed Forces Retirement Home.