Skip to main content

Oil Spill Recovery

Schedules

TAFS: 070-8349 /X - Oil Spill Recovery

Iterations:
Adjustment authority: No
Reporting categories: No
Line #SplitDescriptionIteration 3
Previously Approved Amount
Iteration 4
Current OMB Action Amount
Footnotes
1000AUnob Bal: Brought forward, October 1Line added+$39,825,591
$39,825,591
1000EUnob Bal: Brought forward, October 1$77,619,373-$77,619,373
$0
1021Unob Bal: Recov of prior year unpaid obligationsLine added+$931,969
$931,969
1061Unob Bal: Antic recov of prior year unpd/pd obl$25,000,000-$931,969
$24,068,031
1202BA: Mand: Appropriation (previously unavailable)$0 Line removed
1201BA: Mand: Appropriation (special or trust)$51,000,000-$33,392
$50,966,608
See footnotes below
Footnotes for line 1201 (Current):

B2: This schedule is being submitted to record the actual annual interest amount of $966,607.36.

1203SEQBA: Mand: Appropriation (previously unavailable)$5,757,800 $5,757,800
1232SEQBA: Mand: New\Unob bal of approps temp reduced-$10,032,000+$1,903
-$10,030,097
See footnotes below
Footnotes for line 1232 (SEQ) (Current):

B3: The sequestration amount on line 1232 <$10M> is revised on the apportionment to reflect 5.7% of actual interest received for OSRI ($966,607.36), estimated X8312 FY21 claims payments ($50,000,000), additional emergency response funds ($75,000,000) and X8349 apportioned amount ($50,000,000).

1251BA: Mand: Appropriations:Antic nonexpend trans net$75,000,000 $75,000,000See footnotes below
Footnotes for line 1251 (Previous):

B1: Pursuant to the Oil Spill Pollution Act of 1990, P.L. 101-380 Sec. 6002(b) and 33 U.S.C. 2752 (b)(2) this schedule is being submitted to apportion an advance of additional funding from the Oil Spill Emergency Fund in support of continued oil spill cleanup efforts from the Smitty Supply Company Exploison that occurred in August 2025.

1920Total budgetary resources avail (disc. and mand.)$224,345,173-$37,825,271
$186,519,902
6011Project Emergency Response - Oil Spills and Oil Spill Recovery$224,345,173-$37,825,271
$186,519,902
6012Project Emergency Response - Oil Spills and Oil Spill Recovery$0 Line removed
6190Total budgetary resources available$224,345,173-$37,825,271
$186,519,902
See footnotes below
Footnotes for line 6190 (Previous):

A1: The amount shown on line 1232 (line split "SEQ") is the required sequester amount assuming that the mandatory appropriation is equal to the amount shown on line 1201. If the final appropriation amount is different from the amounts shown on line 1201, then the amount on line 1232 is automatically apportioned so as to reflect 5.7% of the total FY 2026 appropriation. Because of the indefinite nature of this account, the sequestered amount may not be equal to the amount reflected in the OMB Report to the Congress on the Joint Sequestration for Fiscal Year 2026. [Rationale: Footnote signifies that this TAFS has received or may receive an automatic apportionment.]

Footnotes for line 6190 (Current):

A2: The amount shown on line 1232 (line split "SEQ") is the required sequester amount assuming that the mandatory appropriation is equal to the amount shown on line 1201. If the final appropriation amount is different from the amounts shown on line 1201, then the amount on line 1232 is automatically apportioned so as to reflect 5.7% of the total FY 2026 appropriation. Because of the indefinite nature of this account, the sequestered amount may not be equal to the amount reflected in the OMB Report to the Congress on the Joint Sequestration for Fiscal Year 2026. [Rationale: Footnote signifies that this TAFS has received or may receive an automatic apportionment.]

Footnotes

Footnotes provide further information about, or establish further legal requirements related to the use of, the funds in a given line or set of lines in an apportionment. If footnotes appear on lines 1920 or 6190, they apply to all the lines in the 1xxx and 6xxx sections, respectively. The following are all the footnotes associated with this file.

NumberText
A2
The amount shown on line 1232 (line split "SEQ") is the required sequester amount assuming that the mandatory appropriation is equal to the amount shown on line 1201. If the final appropriation amount is different from the amounts shown on line 1201, then the amount on line 1232 is automatically apportioned so as to reflect 5.7% of the total FY 2026 appropriation. Because of the indefinite nature of this account, the sequestered amount may not be equal to the amount reflected in the OMB Report to the Congress on the Joint Sequestration for Fiscal Year 2026. [Rationale: Footnote signifies that this TAFS has received or may receive an automatic apportionment.]
B2
This schedule is being submitted to record the actual annual interest amount of $966,607.36.
B3
The sequestration amount on line 1232 <$10M> is revised on the apportionment to reflect 5.7% of actual interest received for OSRI ($966,607.36), estimated X8312 FY21 claims payments ($50,000,000), additional emergency response funds ($75,000,000) and X8349 apportioned amount ($50,000,000).

The following are all of the footnotes associated with the previous iteration of this file. Note that previous iterations of accounts in this file may come from multiple previous files.

NumberText
A1
The amount shown on line 1232 (line split "SEQ") is the required sequester amount assuming that the mandatory appropriation is equal to the amount shown on line 1201. If the final appropriation amount is different from the amounts shown on line 1201, then the amount on line 1232 is automatically apportioned so as to reflect 5.7% of the total FY 2026 appropriation. Because of the indefinite nature of this account, the sequestered amount may not be equal to the amount reflected in the OMB Report to the Congress on the Joint Sequestration for Fiscal Year 2026. [Rationale: Footnote signifies that this TAFS has received or may receive an automatic apportionment.]
B1
Pursuant to the Oil Spill Pollution Act of 1990, P.L. 101-380 Sec. 6002(b) and 33 U.S.C. 2752 (b)(2) this schedule is being submitted to apportion an advance of additional funding from the Oil Spill Emergency Fund in support of continued oil spill cleanup efforts from the Smitty Supply Company Exploison that occurred in August 2025.

Notes about this page

  • † Links to public laws are automatically generated and are not guaranteed to be accurate.