Skip to main content

Spectrum Relocation Fund

Schedules

TAFS: 011-5512 /X - Spectrum Relocation Fund

Iterations:
Adjustment authority: No
Reporting categories: No
Line #SplitDescriptionIteration 4
Previously Approved Amount
Iteration 5
OMB Action Amount
Footnotes
1011Unobligated bal transferred from other accounts$4,800,000 $4,800,000See footnotes below
Footnotes for line 1011 (Previous):

B4: DOJ returned $4,800,000 in AWS-3 funding from ATF (015-X-0700), and DOJ/JIST will use $4.8 million from the SRF to complete AWS-3 activities (see B1 above). This amount is precluded from obligation during FY 2025.

Footnotes for line 1011 (Current):

B4: DOJ returned $4,800,000 in AWS-3 funding from ATF (015-X-0700), and DOJ/JIST will use $4.8 million from the SRF to complete AWS-3 activities (see B1 above). This amount is precluded from obligation during FY 2025.

1035Unobligated bal precluded from obl (limitation on obl)-$4,800,000 -$4,800,000See footnotes below
Footnotes for line 1035 (Previous):

B4: DOJ returned $4,800,000 in AWS-3 funding from ATF (015-X-0700), and DOJ/JIST will use $4.8 million from the SRF to complete AWS-3 activities (see B1 above). This amount is precluded from obligation during FY 2025.

Footnotes for line 1035 (Current):

B4: DOJ returned $4,800,000 in AWS-3 funding from ATF (015-X-0700), and DOJ/JIST will use $4.8 million from the SRF to complete AWS-3 activities (see B1 above). This amount is precluded from obligation during FY 2025.

10401Anticipated non-expenditure transfers of unob bal$0 $0
10402Anticipated non-expenditure transfers of unob bal$0 $0
1203BA: Mand: Approp (previously unavail) (spec/trust)$686,045,997+$474,288,366
$1,160,334,363
1203SEQAppropriation (previously unavailable)$39,147,589 $39,147,589See footnotes below
Footnotes for line 1203 (SEQ) (Previous):

B2: New budgetary resources in the Spectrum Relocation Fund were subject to sequestration of 5.7% in FY24. $39,147,589 in previously sequestered funds became available in FY 2025.

Footnotes for line 1203 (SEQ) (Current):

B2: New budgetary resources in the Spectrum Relocation Fund were subject to sequestration of 5.7% in FY24. $39,147,589 in previously sequestered funds became available in FY 2025.

1220BA: Mand: Approps transferred to other accounts$0 $0
1221BA: Mand: Approps transferred from other accounts$0 $0
1232BA: Mand: New\Unob bal of approps temp reduced$0 $0
1232SEQBA: Mand: New\Unob bal of approps temp reduced-$39,104,622-$27,034,437
-$66,139,059
See footnotes below
Footnotes for line 1232 (SEQ) (Previous):

B3: New budgetary resources in the Spectrum Relocation Fund are subject to a sequestration rate of 5.7% in FY25. These funds will become available for obligation in FY 2026.

Footnotes for line 1232 (SEQ) (Current):

B3: New budgetary resources in the Spectrum Relocation Fund are subject to a sequestration rate of 5.7% in FY25. These funds will become available for obligation in FY 2026.

1251BA: Mand: Appropriations:Antic nonexpend trans net-$686,088,964-$447,253,929
-$1,133,342,893
See footnotes below
Footnotes for line 1251 (Previous):

B1: Pursuant to statute, on November 23, 2021, OMB submitted a 45 day notice of "subsequent transfers" to Congress of the intent to transfer no more than $293,275,897 in additional transfers to the Department of Justice (DOJ) to complete its AWS-3 transition. OMB apportioned $52,959,040 in FY 2022, $67,893,074 in FY 2023, and $74,588,167 for DOJ's AWS-3 activities, leaving a balance of $97,835,616. The initial apportionment reflects a transfer of $66,625,341 from the SRF to DOJ, which includes $22,605,138 to FBI (15X0200); $35,986,882 to DEA (15X1100); and $8,033,321 to USMS (15X0324) for AWS-3 activities. The second apportionment reflects a transfer of $4,800,000 from the SRF to DOJ/JIST for AWS-3 activities, for a total of $71,425,341 transferred to DOJ year-to-date.

B5: Pursuant to statute, OMB submitted a 45 day notice of "subsequent transfers" to Congress of the intent to transfer no more than $416,727,954 in additional transfers to the Department of Defense for AWS-3 related transition expenses. The letter was transmitted on November 13, 2024, meaning AWS-3 funds could not be transferred before December 30, 2024. During FY 2025, DOD requested $109,558,681 for AWS-3 activities under the third SRF apportionment.

B6: Pursuant to statute, OMB submitted a 45 day notice of "subsequent transfers" to Congress of the intent to transfer no more than $29,304,821 to agencies with systems affected by the Citizens Broadband Radio Service (CBRS) auction (i.e. DOD). The letter was transmitted on November 13, 2024, meaning CBRS funds could not be transferred before December 30, 2024. During FY 2025, DOD requested $12,815,242 for CBRS activities under the third SRF apportionment.

B7: Pursuant to statute, OMB submitted a 45 day notice of "subsequent transfers" to Congress of the intent to transfer no more than $12,639,994,889 to agencies with systems affected by the 3450-3550 MHz auction (i.e. DOD). The letter was transmitted on November 13, 2024, meaning CBRS funds could not be transferred before December 30, 2024. During FY 2025, DOD requested $387,632,407 for 3450-3550 MHz activities under the third SRF apportionment.

B8: Pursuant to statute, OMB submitted a 60 day notice with approved Pipeline plans for the 7-8 GHz Pipeline study totaling $104,657,293 for the following nine Federal entitites: DHS, DOE, DOJ, DOT, USCG, DOI, NASA, NOAA, NSF. (Note this Congressional notification did not include DOD's Pipeline plan, as it was not approved until later.) The letter was transmitted on November 7, 2024, meaning no Pipeline funds could be transferred before January 6, 2025. Details regarding agency transfers are included on the "7-8 GHz Pipeline Xfer details" tab within this apportionment.

Footnotes for line 1251 (Current):

B1: Pursuant to statute, on November 23, 2021, OMB submitted a 45 day notice of "subsequent transfers" to Congress of the intent to transfer no more than $293,275,897 in additional transfers to the Department of Justice (DOJ) to complete its AWS-3 transition. OMB apportioned $52,959,040 in FY 2022, $67,893,074 in FY 2023, and $74,588,167 for DOJ's AWS-3 activities, leaving a balance of $97,835,616. The initial apportionment reflects a transfer of $66,625,341 from the SRF to DOJ, which includes $22,605,138 to FBI (15X0200); $35,986,882 to DEA (15X1100); and $8,033,321 to USMS (15X0324) for AWS-3 activities. The second apportionment reflects a transfer of $4,800,000 from the SRF to DOJ/JIST for AWS-3 activities, for a total of $71,425,341 transferred to DOJ year-to-date.

B5: Pursuant to statute, OMB submitted a 45 day notice of "subsequent transfers" to Congress of the intent to transfer no more than $416,727,954 in additional transfers to the Department of Defense for AWS-3 related transition expenses. The letter was transmitted on November 13, 2024, meaning AWS-3 funds could not be transferred before December 30, 2024. During FY 2025, DOD requested $109,558,681 for AWS-3 activities under the third SRF apportionment. DOD requested $11,247,983 for AWS activities under this fifth SRF apportionment,

B6: Pursuant to statute, OMB submitted a 45 day notice of "subsequent transfers" to Congress of the intent to transfer no more than $29,304,821 to agencies with systems affected by the Citizens Broadband Radio Service (CBRS) auction (i.e. DOD). The letter was transmitted on November 13, 2024, meaning CBRS funds could not be transferred before December 30, 2024. During FY 2025, DOD requested $12,815,242 for CBRS activities under the third SRF apportionment. DOD requested $289,147 for CBRS activties under this fifth SRF apportionment.

B7: Pursuant to statute, OMB submitted a 45 day notice of "subsequent transfers" to Congress of the intent to transfer no more than $12,639,994,889 to agencies with systems affected by the 3450-3550 MHz auction (i.e. DOD). The letter was transmitted on November 13, 2024, meaning CBRS funds could not be transferred before December 30, 2024. During FY 2025, DOD requested $387,632,407 for 3450-3550 MHz activities under the third SRF apportionment. DOD requested $34,825,177 for 3450-3550 MHz actvities under this fifth SRF apportionment.

B8: Pursuant to statute, OMB submitted a 60 day notice with approved Pipeline plans for the 7-8 GHz Pipeline study totaling $104,657,293 for the following nine Federal entitites: DHS, DOE, DOJ, DOT, USCG, DOI, NASA, NOAA, NSF. (Note this Congressional notification did not include DOD's Pipeline plan, as it was not approved until later.) The letter was transmitted on November 7, 2024, meaning no Pipeline funds could be transferred before January 6, 2025. DOD's 7-8 GHz Pipeline plan totaling $159,567,000 was transmitted on January 15, 2025, meaning no DOD Pipeline funds for 7-8 GHz can be transferred before March 17, 2025. The total amount to be transferred in FY 2025 to DOD on this fifth SRF apportionment is $69,470,633. Details regarding agency transfers are included on the "7-8 GHz Pipeline Xfer details" tab within this apportionment.

B9: Pursuant to statute, OMB submitted a 60 day notice with approved Pipeline plans for the 3 GHz Pipeline study totaling $614,310,000 for the following six Federal entities: DOD, DHS, USCG, DOT, NOAA, and NSF. The letter was transmitted on January 15, 2025, meaning no Pipeline funds can be transferred before March 17, 2025. Details regarding agency transfers are included on the "3 GHz Pipeline Xfer detail" tab within this apportionment. The total amount to be transferred in FY 2025 on this fifth SRF apportionment is $331,420,989, of which $277,544,989 is for DOD and $53,876,000 is for DHS, USCG, DOT, NOAA, and NSF.

1920Total budgetary resources avail (disc. and mand.)$0 $0
6190Total budgetary resources available$0 $0

Footnotes

Footnotes provide further information about, or establish further legal requirements related to the use of, the funds in a given line or set of lines in an apportionment. If footnotes appear on lines 1920 or 6190, they apply to all the lines in the 1xxx and 6xxx sections, respectively. The following are all the footnotes associated with this file.

NumberText
B1
Pursuant to statute, on November 23, 2021, OMB submitted a 45 day notice of "subsequent transfers" to Congress of the intent to transfer no more than $293,275,897 in additional transfers to the Department of Justice (DOJ) to complete its AWS-3 transition. OMB apportioned $52,959,040 in FY 2022, $67,893,074 in FY 2023, and $74,588,167 for DOJ's AWS-3 activities, leaving a balance of $97,835,616. The initial apportionment reflects a transfer of $66,625,341 from the SRF to DOJ, which includes $22,605,138 to FBI (15X0200); $35,986,882 to DEA (15X1100); and $8,033,321 to USMS (15X0324) for AWS-3 activities. The second apportionment reflects a transfer of $4,800,000 from the SRF to DOJ/JIST for AWS-3 activities, for a total of $71,425,341 transferred to DOJ year-to-date.
B2
New budgetary resources in the Spectrum Relocation Fund were subject to sequestration of 5.7% in FY24. $39,147,589 in previously sequestered funds became available in FY 2025.
B3
New budgetary resources in the Spectrum Relocation Fund are subject to a sequestration rate of 5.7% in FY25. These funds will become available for obligation in FY 2026.
B4
DOJ returned $4,800,000 in AWS-3 funding from ATF (015-X-0700), and DOJ/JIST will use $4.8 million from the SRF to complete AWS-3 activities (see B1 above). This amount is precluded from obligation during FY 2025.
B5
Pursuant to statute, OMB submitted a 45 day notice of "subsequent transfers" to Congress of the intent to transfer no more than $416,727,954 in additional transfers to the Department of Defense for AWS-3 related transition expenses. The letter was transmitted on November 13, 2024, meaning AWS-3 funds could not be transferred before December 30, 2024. During FY 2025, DOD requested $109,558,681 for AWS-3 activities under the third SRF apportionment. DOD requested $11,247,983 for AWS activities under this fifth SRF apportionment,
B6
Pursuant to statute, OMB submitted a 45 day notice of "subsequent transfers" to Congress of the intent to transfer no more than $29,304,821 to agencies with systems affected by the Citizens Broadband Radio Service (CBRS) auction (i.e. DOD). The letter was transmitted on November 13, 2024, meaning CBRS funds could not be transferred before December 30, 2024. During FY 2025, DOD requested $12,815,242 for CBRS activities under the third SRF apportionment. DOD requested $289,147 for CBRS activties under this fifth SRF apportionment.
B7
Pursuant to statute, OMB submitted a 45 day notice of "subsequent transfers" to Congress of the intent to transfer no more than $12,639,994,889 to agencies with systems affected by the 3450-3550 MHz auction (i.e. DOD). The letter was transmitted on November 13, 2024, meaning CBRS funds could not be transferred before December 30, 2024. During FY 2025, DOD requested $387,632,407 for 3450-3550 MHz activities under the third SRF apportionment. DOD requested $34,825,177 for 3450-3550 MHz actvities under this fifth SRF apportionment.
B8
Pursuant to statute, OMB submitted a 60 day notice with approved Pipeline plans for the 7-8 GHz Pipeline study totaling $104,657,293 for the following nine Federal entitites: DHS, DOE, DOJ, DOT, USCG, DOI, NASA, NOAA, NSF. (Note this Congressional notification did not include DOD's Pipeline plan, as it was not approved until later.) The letter was transmitted on November 7, 2024, meaning no Pipeline funds could be transferred before January 6, 2025. DOD's 7-8 GHz Pipeline plan totaling $159,567,000 was transmitted on January 15, 2025, meaning no DOD Pipeline funds for 7-8 GHz can be transferred before March 17, 2025. The total amount to be transferred in FY 2025 to DOD on this fifth SRF apportionment is $69,470,633. Details regarding agency transfers are included on the "7-8 GHz Pipeline Xfer details" tab within this apportionment.
B9
Pursuant to statute, OMB submitted a 60 day notice with approved Pipeline plans for the 3 GHz Pipeline study totaling $614,310,000 for the following six Federal entities: DOD, DHS, USCG, DOT, NOAA, and NSF. The letter was transmitted on January 15, 2025, meaning no Pipeline funds can be transferred before March 17, 2025. Details regarding agency transfers are included on the "3 GHz Pipeline Xfer detail" tab within this apportionment. The total amount to be transferred in FY 2025 on this fifth SRF apportionment is $331,420,989, of which $277,544,989 is for DOD and $53,876,000 is for DHS, USCG, DOT, NOAA, and NSF.

The following are all of the footnotes associated with the previous iteration of this file. Note that previous iterations of accounts in this file may come from multiple previous files.

NumberText
B1
Pursuant to statute, on November 23, 2021, OMB submitted a 45 day notice of "subsequent transfers" to Congress of the intent to transfer no more than $293,275,897 in additional transfers to the Department of Justice (DOJ) to complete its AWS-3 transition. OMB apportioned $52,959,040 in FY 2022, $67,893,074 in FY 2023, and $74,588,167 for DOJ's AWS-3 activities, leaving a balance of $97,835,616. The initial apportionment reflects a transfer of $66,625,341 from the SRF to DOJ, which includes $22,605,138 to FBI (15X0200); $35,986,882 to DEA (15X1100); and $8,033,321 to USMS (15X0324) for AWS-3 activities. The second apportionment reflects a transfer of $4,800,000 from the SRF to DOJ/JIST for AWS-3 activities, for a total of $71,425,341 transferred to DOJ year-to-date.
B2
New budgetary resources in the Spectrum Relocation Fund were subject to sequestration of 5.7% in FY24. $39,147,589 in previously sequestered funds became available in FY 2025.
B3
New budgetary resources in the Spectrum Relocation Fund are subject to a sequestration rate of 5.7% in FY25. These funds will become available for obligation in FY 2026.
B4
DOJ returned $4,800,000 in AWS-3 funding from ATF (015-X-0700), and DOJ/JIST will use $4.8 million from the SRF to complete AWS-3 activities (see B1 above). This amount is precluded from obligation during FY 2025.
B5
Pursuant to statute, OMB submitted a 45 day notice of "subsequent transfers" to Congress of the intent to transfer no more than $416,727,954 in additional transfers to the Department of Defense for AWS-3 related transition expenses. The letter was transmitted on November 13, 2024, meaning AWS-3 funds could not be transferred before December 30, 2024. During FY 2025, DOD requested $109,558,681 for AWS-3 activities under the third SRF apportionment.
B6
Pursuant to statute, OMB submitted a 45 day notice of "subsequent transfers" to Congress of the intent to transfer no more than $29,304,821 to agencies with systems affected by the Citizens Broadband Radio Service (CBRS) auction (i.e. DOD). The letter was transmitted on November 13, 2024, meaning CBRS funds could not be transferred before December 30, 2024. During FY 2025, DOD requested $12,815,242 for CBRS activities under the third SRF apportionment.
B7
Pursuant to statute, OMB submitted a 45 day notice of "subsequent transfers" to Congress of the intent to transfer no more than $12,639,994,889 to agencies with systems affected by the 3450-3550 MHz auction (i.e. DOD). The letter was transmitted on November 13, 2024, meaning CBRS funds could not be transferred before December 30, 2024. During FY 2025, DOD requested $387,632,407 for 3450-3550 MHz activities under the third SRF apportionment.
B8
Pursuant to statute, OMB submitted a 60 day notice with approved Pipeline plans for the 7-8 GHz Pipeline study totaling $104,657,293 for the following nine Federal entitites: DHS, DOE, DOJ, DOT, USCG, DOI, NASA, NOAA, NSF. (Note this Congressional notification did not include DOD's Pipeline plan, as it was not approved until later.) The letter was transmitted on November 7, 2024, meaning no Pipeline funds could be transferred before January 6, 2025. Details regarding agency transfers are included on the "7-8 GHz Pipeline Xfer details" tab within this apportionment.

Notes about this page